Several elements including structural components, plant room walls, pods, façade cladding and glide-on balconies were utilised. This resulted in a significant reduction in site traffic and related carbon emissions, waste and disruption. For example, installation of the precast facades and balconies was faster, safer and required significantly less labour, completed in 96 days with 13 operatives, compared to 200 days with 40 operatives for an equivalent hand-set brick building.